Bond 2021 Projects

Project Breakdown

☑ - Complete
☐ - In Design or Under Construction

☑  Redesigned front entry for enhanced security

☑  Additional security cameras/devices

☑  Replacement of PA/intercom system

☑  Mechanical/HVAC upgrades, including controls

☑  Interior refurbishments including paint, ceiling and flooring in key areas

☑  Expansion or improvements to conditions at parent drop off and bus queuing lanes, including sidewalks

☑  Addition/upgrade of fabric canopies at playgrounds

 

 

Overall LPES Bond 2021 Project Status

Complete


Estimated Construction Timeline
Start: Fall 2022
Finish: Summer 2024

Funding Source
2021 Bond