• Cedar Creek High School

  • Exterior of Cedar Creek High School

  • Renovations for Cedar Creek High School. A team of district employees, stakeholders, and community members worked together to create the Cedar Creek High School Master Plan. 

  • Bond 2021 Projects

Project Breakdown

  • - Complete
    ☐ - In Design or Under Construction

      Addition of classrooms to increase capacity to 2,100

      Special security curtains for classrooms with glass walls

      Additional security cameras/devices

      Display space in common areas

      Ventilation to sound rooms for band

      Repair of bleachers in main gym

      Mechanical/HVAC upgrades, including controls

      Drainage and fencing improvements

      General campus refurbishments

      New flooring in field house

  • Overall CCHS Bond 2021 Project Status
    Complete

    Estimated Construction Timeline
    Start: Fall 2022
    Finish: Summer 2024

    Funding Source
    2021 Bond

Related Projects

  • General Improvements
  • Safety & Security

  •  


  •  

    Bond 2023 Projects

Project Breakdown

  • - Complete
    ☐ - In Design or Under Construction

      New wing to add 20 classrooms

      Practice site for marching band

       Additional security cameras

      HVAC in weight room & field house

     

     

  • Overall CCHS Bond 2023 Project Status
    In Design / Permitting
     On Schedule

    Estimated Construction Timeline
    Start: Fall 2024
    Finish: Fall 2025

    Funding Source
    2023 Bond